Question: A project team is required to prepare a monthly project update report for the project key stakeholders. This report must contain the current status of


A project team is required to prepare a monthly project update report for the project key stakeholders. This report must contain the current status of the deliverables, information related to the recently approved change requests, project's health and the forecasted estimates. This report is an example of?

A. Milestone B. Expert judgment C. Work performance information D. Work performance data