Question: A variance threshold for costs or other indicators to indicate the agreed amount of variation allowed is called: A. Upper specification limit B. Control thresholds
A variance threshold for costs or other indicators to indicate the agreed amount of variation allowed is called:
A. Upper specification limit B. Control thresholds C. Upper control limits D. Cost overrun