Question: As a project manager, you periodically do project performance reviews to compare cost performance over time, schedule activities or work packages over-running and under-running budget,
As a project manager, you periodically do project performance reviews to compare cost performance over time, schedule activities or work packages over-running and under-running budget, milestones due, and milestones met. Which of the following is not a valid analytical technique?
A. Trend Analysis B. Earned Value Performance C. Variance Analysis D. Interpersonal skills