Question: After measuring expected project benefits, your project management office has four projects from which to choose. Project A has a NPV of $160,000 and will
After measuring expected project benefits, your project management office has four projects from which to choose. Project A has a NPV of $160,000 and will cost $10,000. Project B has a NPV of $470,000 and will cost $220,000. Project C has a NPV of $265,000 and will cost $33,000. Project D has a NPV of $335,000 and will cost $57,000.
Which project would be BEST?
A: Project C B: Project A C: Project B D: Project D