Question: You are choosing between two potential projects that your organization could undertake. The first project, Project Eagle , will cost $500,000 and will have a
You are choosing between two potential projects that your organization could undertake. The first project, Project Eagle , will cost $500,000 and will have a NPV of $50,000. The second project, Project Falcon, will cost $420,000 and will have a NPV of
$48,000. Which of the two projects should you do?
A: Do not have enough information to answer this question.
B: Project Falcon.
C: Project Eagle.
D: Neither project meets NPV criteria.