Question: An approved change request impacting project scope is: A. Any modification in technical specifications as defined in the WBS. B. Any change in project authorization.
An approved change request impacting project scope is: A. Any modification in technical specifications as defined in the WBS. B. Any change in project authorization. C. Any change in project personnel. D. Any modification to the agreed-upon project scope baseline, as defined by the approved project scope statement, WBS, and WBS dictionary.