Question: As the project manager, you are preparing your methods for quality management. You are looking for a method that can demonstrate the relationship between events

As the project manager, you are preparing your methods for quality management. You are looking for a method that can demonstrate the relationship between events and their resulting effects. You want to use a method to depict the events that cause a negative effect on quality. Which of the following is the BEST choice for accomplishing your objective? A. Histogram B. Pareto chart C. Ishikawa diagram D. Control chart