Question: Assume that on your project, you are using earned value management. Your project is one that has extremely long work packages. Therefore, the method you
Assume that on your project, you are using earned value management. Your project is one that has extremely long work packages. Therefore, the method you should use to calculate EV is—
a. 0/100 rule
b. Milestone method
c. Equivalent effort
d. Apportioned effort