Question: Assuming your past performance will be the same as the future performance, you have calculated the EAC as 250,000 USD. Your previous budget was 200,000
Assuming your past performance will be the same as the future performance, you have calculated the EAC as 250,000 USD. Your previous budget was 200,000 USD and you have earned 50,000 USD to date. What is the money spent to date?
(a) 40,000 USD
(b) 50,000 USD
(c) 90,000 USD
(d) 62,500 USD
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts