Question: Based on the table shown below identify the Critical Path (draw the network diagram considering day 1 as the first day of the project. Answers

Based on the table shown below identify the Critical Path (draw the network diagram considering day 1 as the first day of the project. Answers to questions are based on the diagram considering day 1 as the first day of the project).Activity Name Predecessor Duration Start A Start 5 B A 10 C

(a) Path HIJ

(b) Path ABFG

(c) Path EFG

(d) Path ABCD

Activity Name Predecessor Duration Start A Start 5 B A 10 C B 15 D C 10 EFG Start 5 B, E 4 H F Start 6 6 I E, H 5 J T 4 Finish D, G, J