Question: Daniel is the project manager for a factory construction project. Daniel has recently joined this organization and is not fully aware of the organization's culture
Daniel is the project manager for a factory construction project. Daniel has recently joined this organization and is not fully aware of the organization's culture and structure. In order to manage his project stakeholders, Daniel has to understand his project stakeholders better. Which of the following can provide Daniel some historical information regarding stakeholder management on previous projects?
A. Project management plan B. Enterprise environmental factors C. Organizational process assets D. Project charter