Question: Decomposition is a technique used for both WBS development and activity definition. Which following statement best describes the role decomposition plays in activity definition as

Decomposition is a technique used for both WBS development and activity definition. Which following statement best describes the role decomposition plays in activity definition as compared to creating the WBS?

a. Final output is described in terms of work packages in the WBS.

b. Final output is described as deliverables or tangible items.

c. Final output is described as schedule activities.

d. Decomposition is used the same way in scope definition and activity definition.