Question: Flag question: Question 36 Question 361 pts What is an output of the Acquire Project Team process and is used to stipulate when people are
Flag question: Question 36Question 361 pts
What is an output of the Acquire Project Team process and is used to stipulate when people are allocated to the project team? (LO-9)
Group of answer choices
Resource calendars
Project staff assignments
Project management plan updates
Human resource management plan
Flag question: Question 37Question 371 pts
Which input contains forecasting data that is used by the Monitor Risks process? (LO-11)
Group of answer choices
Work performance reports
Work performance information
Team performance assessments
Work performance data
Flag question: Question 38Question 381 pts
What is best to use during the Manage Quality process when you need to identify where improvements can be made to project processes? (LO-8)
Group of answer choices
Process analysis
Alternative analysis
Design for X
Audits
Flag question: Question 39Question 391 pts
Which statement BEST describes technical project management skills? (LO-3)
Group of answer choices
The ability to create the project work breakdown structure (WBS)
The ability to inspire and motivate the project team
The ability to write code on a software project
The ability to explain the business value of the project
Flag question: Question 40Question 401 pts
Which process is responsible for decomposing work packages into tasks so that project work can be estimated? (LO-6)
Group of answer choices
Create WBS
Develop Project Charter
Estimate Activity Durations
Define Activities
Flag question: Question 41Question 411 pts
Which document is used to formally authorize the project? (LO-4)
Group of answer choices
Business case
Project management plan
Project statement of work
Project charter
Flag question: Question 42Question 421 pts
Which tool or technique is used by the Monitor Risks process to determine whether there are enough funds set aside to cover the amount of risk remaining in the project? (LO-11)
Group of answer choices
Meetings
Reserve analysis
Audits
Technical performance analysis
Flag question: Question 43Question 431 pts
Which process enables the allocation of clear responsibilities for each work unit that is required by the project? (LO-6)
Group of answer choices
Define Activities
Create WBS
Estimate Activity Resources
Develop Schedule
Flag question: Question 44Question 441 pts
Which Process Group contains the processes used to gain authorization to start a new project phase? (LO-1)
Group of answer choices
Executing
Monitoring and Controlling
Initiating
Planning
Flag question: Question 45Question 451 pts
How do the top two percent of project managers distinguish themselves from other project managers? (LO-3)
Group of answer choices
Superior planning skills
Superior technical skills
Superior forecasting skills
Superior communication skills
Flag question: Question 46Question 461 pts
Which process uses the colocation technique? (LO-9)
Group of answer choices
Manage Project Team
Plan Human Resource Management
Develop Project Team
Acquire Project Team
Flag question: Question 47Question 471 pts
Which item represents the inputs to the Plan Communications Management process? (LO-10)
Group of answer choices
Organizational process assets, the project management plan, and the stakeholder register
The project management plan, team charter, and the stakeholder register
Enterprise environmental factors, the project management plan, and team charter
Enterprise environment factors, organizational process assets, and issue log
Flag question: Question 48Question 481 pts
Identify the project type that would benefit most from detailed cost estimation methods in agile/adaptive environments. (LO-7)
Group of answer choices
A project in which the scope is not completely defined
A project in which the labor cost estimation can be easily adjusted, if needed
A project with a short-term planning range
A project with a high level of uncertainty
Flag question: Question 49Question 491 pts
Which output of the Plan Quality Management process details quality requirements that may need to be updated? (LO-8)
Group of answer choices
Quality management plan
Checklists
Scope baseline
Quality metrics
Flag question: Question 50Question 501 pts
Which input of the Estimate Activity Durations process provides details on when a piece of equipment is available, and for how long it will be available during a project? (LO-6)
Group of answer choices
Resource calendar
Activity attributes
Organizational process assets
Activity list
Flag question: Question 51Question 511 pts
Which document is used for making decision results from monitoring the execution of project activities? (LO-4)
Group of answer choices
Work performance reports
Team performance assessments
Project calendars
Quality checklists
Flag question: Question 52Question 521 pts
A project manager determines that two days of lead-time can be placed on one of its activities on the project's critical path. What effect can this lead-time have on this project? (LO-6)
Group of answer choices
It can increase the overall project schedule and decrease the risk.
It can decrease the overall project schedule and increase the risk.
It can decrease the overall project schedule and decrease the risk.
It can increase the overall project schedule and increase the risk.
Flag question: Question 53Question 531 pts
Which input to the Control Scope process contains the information that actual results are compared to when determining if a change is required? (LO-5)
Group of answer choices
Requirements documentation
Work performance data
Project management plan
Requirements traceability matrix
Flag question: Question 54Question 541 pts
Which Process Group contains the processes that are responsible for generating work performance data? (LO-1)
Group of answer choices
Monitoring and Controlling
Planning
Executing
Closing
Flag question: Question 55Question 551 pts
Deliverable status and performance reports are examples of which output from the Manage Communications process? (LO-10)
Group of answer choices
Project management plan updates
Bid documents
Project communications
Work performance data
Flag question: Question 56Question 561 pts
Which of the following conflict management techniques often results in a win-lose situation? (LO-9)
Group of answer choices
Smooth/accommodate
Force/direct
Collaborate/problem solve
Withdraw/avoid
Flag question: Question 57Question 571 pts
Lessons learned register and stakeholder register are examples of which output from the Monitor Communications process? (LO-10)
Group of answer choices
Project documents updates
Organizational process assets updates
Change requests
Project management plan updates
Flag question: Question 58Question 581 pts
Which project cost management process makes use of the following data analysis techniques: earned value analysis, variance analysis, trend analysis, and reserve analysis? (LO-7)
Group of answer choices
Control costs
Estimate costs
Determine budget
Plan cost management
Flag question: Question 59Question 591 pts
Which Process Group contains the activities used to record the effects of tailoring the processes to the project environment? (LO-1)
Group of answer choices
Planning
Executing
Closing
Monitoring and Controlling
Flag question: Question 60Question 601 pts
Which input of the Control Scope process is used to determine the impact that deviations in the agreed project scope will have on the project objectives? (LO-5)
Group of answer choices
Requirements documentation
Requirements traceability matrix
Work performance data
Project management plan
Flag question: Question 61Question 611 pts
Which tools and techniques are used by the Manage Team process? (LO-9)
Group of answer choices
Emotional intelligence, meetings, and recognition and rewards
Leadership, project management information system, and project team assignments
Project management information system, conflict management, and interpersonal and team skills
Influencing, interpersonal and team skills, and change requests
Flag question: Question 62Question 621 pts
Being involved in expanding the number of peers and business contacts is an example of which power? (LO-3)
Group of answer choices
Persuasive
Relational
Expert
Ingratiating
Flag question: Question 63Question 631 pts
The following are key functions or principles of general management in the organization EXCEPT: (LO-2)
Group of answer choices
Discipline of action
Unity of direction
Support of project manager
Unity of command
Flag question: Question 64Question 641 pts
Which option represents three inputs to the Monitor and Control Project Work process? (LO-1)
Group of answer choices
Project management plan, project funding requirements, and work performance data
Project management plan, cost forecasts, and work performance information
Project management plan, agreements, and work performance data
Project management plan, risk register, and work performance reports
Flag question: Question 65Question 651 pts
What is used during the Define Scope process to identify different approaches that can be used to perform the work required to achieve the project goals? (LO-5)
Group of answer choices
Context diagrams
Alternatives analysis
Multicriteria decision analysis
Product analysis
Flag question: Question 66Question 661 pts
Which item represents an input for the Define Activities process? (LO-6)
Group of answer choices
Activity list
Risk register
Resource calendars
Scope baseline
Flag question: Question 67Question 671 pts
Which organizational structure contains full-time project managers with moderate authority, and includes full-time project administrative staff? (LO-2)
Group of answer choices
Projectized
Strong matrix
Balanced matrix
Weak matrix
Flag question: Question 68Question 681 pts
What correctly identifies the main difference between a project and an operation? (LO-1)
Group of answer choices
A project is temporary and repetitive, and an operation is unique and ongoing.
A project is temporary and unique, and an operation is repetitive and ongoing.
A project does not have limited resources, and an operation has limited resources.
A project has a limited amount of resources, and an operation does not have limited resources.
Flag question: Question 69Question 691 pts
What conclusion can you draw if you're presented with a project schedule network diagram that includes multiple successor activities? (LO-6)
Group of answer choices
There is a path divergence
The activities are at greater risk
There is a path convergence
The activities are affected by multiple activities
Flag question: Question 70Question 701 pts
Which of the following is a characteristic of Project Integration Management? (LO-4)
Group of answer choices
Empowers the senior management and the project management office to finalize benefits management activities
Provides the project management plan to successfully carry out the project objectives
Ensures that processes are performed in a linear fashion to ensure they are completed efficiently
Delegates management of some integration tasks to specialists
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
