Question: During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project.

During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contains detailed descriptions of work packages?

A. WBS dictionary B. Activity list C. Project scope statement D. Scope management plan