Question: During project executing, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the
During project executing, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?
Question options:
WBS Dictionary
Activity Lis
Project scope statement
Scope management plan