Question: During your accounting software implementation project, two project team members have difficulty working together. They come to you, the project manager, for help resolving the

During your accounting software implementation project, two project team members have difficulty working together. They come to you, the project manager, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. This type of management probably indicates you are working in what type of organizational structure? A. Functional B. Weak matrix C. Balanced matrix D. Projectized