Question: During your accounting software implementation project, you find that training is not progressing as quickly as the schedule requires and the users are not well
During your accounting software implementation project, you find that training is not progressing as quickly as the schedule requires and the users are not well trained after the sessions are over. After investigating the cause, you find that the trainers you have retained do not have the proper experience and knowledge to effectively train your users. Which statement best describes the effect on the project and the effect of the action required to fix the problem ? A. The schedule is suffering. To fix the situation, you will have to hire more experienced trainers and schedule extra training sessions. Your schedule will return to planned values while cost will increase. B. The quality and schedule are being negatively impacted. To fix the situation, you will likely have to hire more experienced trainers at a higher rate and schedule extra training sessions. Quality and schedule will return to planned values while cost will increase. C. This problem is the responsibility of the organization that provided the trainers. They will provide replacement trainers who are qualified at the same price to continue the training required.
D. Although your training looks like it is behind schedule, you wisely built in enough slack time to cover such a problem. You simply find replacement trainers and continue the training.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts