Question: - ''h i.:h oft he follow mg is correct? /. 1l1c critic.ii path helps prove how long the project will take. B. 1here can be

- \'\'h i.:h oft he follow mg is correct?

/\. 1l1c critic.ii path helps prove how long the project will take.

B. 1here can be only one critical path.

C. Th(' network diagram will change every time the encl elate ch.mges.

D. A project can never have negative float.