Question: How can changes be made to a project management plan once it has been baselined by the project manager? A. By generating a change request


How can changes be made to a project management plan once it has been baselined by the project manager?

A. By generating a change request and having it approved through the Perform Integrated Change Control process.

B. This is typically done by using a version control system. The project manager creates a new version with the changes and baselines it as the new baseline.

C. This is done by maintaining a revision history or log. The project manager documents the changes in detail and then baselines it.

D. A project management plan cannot be changed once it has been baselined. An addendum has to be created to incorporate the changes.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!