Question: The key input of performing integrated change control Process is: A. A project management plan update B. change requests C. Deliverables D. approved change requests
The key input of performing integrated change control Process is:
A. A project management plan update
B. change requests
C. Deliverables
D. approved change requests
project team that operates with a full-time project manager as
A. Balanced matrix
B. Functional
C. Strong matrix
D. Project-oriented
The project baseline is not yet set. However, a key stakeholder just discovered a critical omission and requests an adjustment to the project management plan. What should you do next as the project manager
A. refuse to make the change
B. Consult the change control board
C. Implement a formal change request
D. Make the adjustment
Design/Build High Rise Tower project can follow Predictive approach during the Design Stage and Agile approach during Construction stage
A. True
B. False