Question: In the first attempt at resource leveling the project schedule, what would you expect to occur? A: The overall project duration will increase. B: The
In the first attempt at resource leveling the project schedule, what would you expect to occur?
A: The overall project duration will increase.
B: The number of required resources will decrease during certain time periods of the project.
C: The number of required resources will increase during certain time periods of the project.
D: The overall project duration will decrease.