Question: You are the project manager on a software project. While examining your schedule you see that there has been a delay in completing a task.

You are the project manager on a software project. While examining your schedule you see that there has been a delay in completing a task. The sensible choice seems to move a person, someone who is an expert on the work that is behind, from another task. There is a choice between two people who are working on different tasks. One person is working on a task that has 5 days of free float and the other is working on a task that has 8 days of total float and no free float. What is your BEST course of action?

A: A person should be brought in from outside the project.

B: The person working on the task with total float of 8 days.

C: Either person can be used.

D: The person working on the task with free float of 5 days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!