Question: You are the project manager on a software project. While examining your schedule you see that there has been a delay in completing a task.
You are the project manager on a software project. While examining your schedule you see that there has been a delay in completing a task. The sensible choice seems to move a person, someone who is an expert on the work that is behind, from another task. There is a choice between two people who are working on different tasks. One person is working on a task that has 5 days of free float and the other is working on a task that has 8 days of total float and no free float. What is your BEST course of action?
A: A person should be brought in from outside the project.
B: The person working on the task with total float of 8 days.
C: Either person can be used.
D: The person working on the task with free float of 5 days.