Question: In your project, two important stakeholders are having some issues. To keep this issue from escalating further you intervene and resolve the issue. After the
In your project, two important stakeholders are having some issues. To keep this issue from escalating further you intervene and resolve the issue. After the issue is resolved you asked your team member to record the issue so in the future a lesson can be learned from it. Where will you note the issues between stakeholders?
(a) Risk register
(b) Issue log
(c) Stakeholder register
(d) Change log