Question: Most project management software packages use a method of constructing a project schedule network diagram known as: A. Activity Diagramming Method B. Precedence Diagramming Method
Most project management software packages use a method of constructing a project schedule network diagram known as:
A. Activity Diagramming Method B. Precedence Diagramming Method C. Project Diagramming Method D. Critical Diagramming Method