Question: PMBOK recognizes five process groups typical of almost all projects. Which of the following is not one of them? A. Executing B. Monitoring and Controlling


PMBOK recognizes five process groups typical of almost all projects. Which of the following is not one of them?

A. Executing B. Monitoring and Controlling C. Planning D. Pre-Inception