Question: A technique that calculates multiple project durations with different sets of activity assumptions and variables is called: A. Process analysis B. Theoretical Analysis C. Simulation
A technique that calculates multiple project durations with different sets of activity assumptions and variables is called:
A. Process analysis B. Theoretical Analysis C. Simulation D. Effect Analysis