Question: Question: An organization has a project with an initial budget of $1,000,000. It is half complete and has spent $2,000,000. Should the organization consider that
Question:
An organization has a project with an initial budget of $1,000,000. It is half complete and has spent $2,000,000.
Should the organization consider that it is already $1,000,000 over budget in determining whether to continue with the project?