Question: Rework required, causes for rejection, and the need for process adjustment are examples of a. Work performance data in Perform Quality Assurance b. Work performance
Rework required, causes for rejection, and the need for process adjustment are examples of—
a. Work performance data in Perform Quality Assurance
b. Work performance information in Control Quality
c. Items that are part of the process improvement plan
d. Items to cover at meetings used to prepare the quality management and process improvement plans