Question: Which is a key benefit of the Control Schedule process? Question 1 options: Reduces rework Provides the means to recognize deviation from the plan Schedule
Which is a key benefit of the Control Schedule process?
Question options:
Reduces rework
Provides the means to recognize deviation from the plan
Schedule compression
Makes changes to the Project Management Plan
Question points
Saved
Updating the schedule model requires:
Question options:
output from the control scope process.
risk register.
activity resource requirements.
knowing the actual performance to date.
Question points
Saved
Which is not a data input to the Control Schedule process?
Question options:
Direct and Manage Project Work
EnterpriseOrganization
Perform Integrated Change Control
Develop Project Management Plan
Question points
Saved
Fast tracking is a technique used to shorten the schedule by:
Question options:
adding resources.
reducing scope.
doing tasks in parallel.
changing the critical path.
Question points
Saved
Schedule performance reviews include all of the following except:
Question options:
earned value management.
critical path method.
trend analysis.
fast tracking.
Question points
Saved
Change requests outputs from the Control Scope process are:
Question options:
reviewed in the work performance data.
reviewed in the Perform Integrated Change Control process.
sent directly to the Direct and Manage Project Work process.
reviewed in the Quality Assurance process.
Question points
Saved
Fast tracking for schedule compression works for:
Question options:
activities behind schedule.
only activities that can be overlapped to shorten the project duration.
activities ahead of schedule.
any activities.
Question points
Saved
Control Schedule is in the Process Group.
Question options:
Planning
Executing
Monitoring and Controlling
Closing
Question points
Saved
Taking corrective and preventive actions in controlling the schedule:
Question options:
transfers risk.
minimizes risk.
mitigates risk.
increases risk.
Question points
If the agile approach is utilized, control schedule is concerned with:
Question options:
fast tracking activities.
reprioritizing the remaining work.
the same as standard projects.
crashing activities.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock