Question: Which is a key benefit of the Control Schedule process? Question 1 options: Reduces rework Provides the means to recognize deviation from the plan Schedule

Which is a key benefit of the Control Schedule process?
Question 1 options:
Reduces rework
Provides the means to recognize deviation from the plan
Schedule compression
Makes changes to the Project Management Plan
Question 2(2 points)
Saved
Updating the schedule model requires:
Question 2 options:
output from the control scope process.
risk register.
activity resource requirements.
knowing the actual performance to date.
Question 3(2 points)
Saved
Which is not a data input to the Control Schedule process?
Question 3 options:
Direct and Manage Project Work
Enterprise/Organization
Perform Integrated Change Control
Develop Project Management Plan
Question 4(2 points)
Saved
Fast tracking is a technique used to shorten the schedule by:
Question 4 options:
adding resources.
reducing scope.
doing tasks in parallel.
changing the critical path.
Question 5(2 points)
Saved
Schedule performance reviews include all of the following except:
Question 5 options:
earned value management.
critical path method.
trend analysis.
fast tracking.
Question 6(2 points)
Saved
Change requests outputs from the Control Scope process are:
Question 6 options:
reviewed in the work performance data.
reviewed in the Perform Integrated Change Control process.
sent directly to the Direct and Manage Project Work process.
reviewed in the Quality Assurance process.
Question 7(2 points)
Saved
Fast tracking for schedule compression works for:
Question 7 options:
activities behind schedule.
only activities that can be overlapped to shorten the project duration.
activities ahead of schedule.
any activities.
Question 8(2 points)
Saved
Control Schedule is in the __________ Process Group.
Question 8 options:
Planning
Executing
Monitoring and Controlling
Closing
Question 9(2 points)
Saved
Taking corrective and preventive actions in controlling the schedule:
Question 9 options:
transfers risk.
minimizes risk.
mitigates risk.
increases risk.
Question 10(2 points)
If the agile approach is utilized, control schedule is concerned with:
Question 10 options:
fast tracking activities.
reprioritizing the remaining work.
the same as standard projects.
crashing activities.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!