Question: Risk mitigation involves a. Using performance and payment bonds b. Eliminating a specific threat by eliminating the cause c. Avoiding the schedule risk inherent in
Risk mitigation involves—
a. Using performance and payment bonds
b. Eliminating a specific threat by eliminating the cause
c. Avoiding the schedule risk inherent in the project
d. Reducing the probability and/or impact of an adverse risk event to an acceptable threshold