Question: When managing current projects, it is important to use lessons learned from previous projects to improve the organizations project management process. Therefore, in project closing
When managing current projects, it is important to use lessons learned from previous projects to improve the organization’s project management process. Therefore, in project closing procedures, it is important to review the—
a. Secondary risks that occurred
b. Checklists for identify risks
c. WBS dictionary
d. Fallback plan