Question: Sensitivity analysis helps to determine which risks have the most potential impact on the project. A project manager prepared a display chart of sensitivity analysis


Sensitivity analysis helps to determine which risks have the most potential impact on the project. A project manager prepared a display chart of sensitivity analysis for his project. The diagram contained a series of bars with the length of the bars corresponding to the risk impact on the project. The longer the bars, the greater was the risk presented. Such a diagram is likely to be:

A. An assessment diagram B. A triangular distribution C. A tornado diagram D. A funnel distribution