Question: Your team is completing an exercise to determine which risks have the greatest potential impact on your project. They are assessing the extent to which

Your team is completing an exercise to determine which risks have the greatest potential impact on your project. They are assessing the extent to which the uncertainty of each element of the project affects the risk being examined when all other uncertain elements are held at static baseline values. What is this technique commonly known as?

A: Tornado diagram B: Expected monetary value analysis C: Sensitivity analysis D: Modeling and simulation