Question: The Critical Path Method is used in project work to: a) Identify the shortest time in which a project can be completed b) Determine the
The Critical Path Method is used in project work to:
a) Identify the shortest time in which a project can be completed
b) Determine the cost of the project
c) Allocate tasks to team members
d) Communicate with stakeholders