Question: This assignment is meant for you to practice the critical path method. Use the PDM network diagramming method to determine the critical time for the

This assignment is meant for you to practice the critical path method. Use the PDM network diagramming method to determine the critical time for the project below.
You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 21 days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than the agreed 21 days.
Draw a project network given the information below. Then, do the following:
1. Complete the forward and backward pass
2. Determine the critical path
3. Compute the Total slack for all activities
4. Determine which activities have free float
Then answer the following questions.
ID
Activity
Predecessor
Duration
A
Prepare Site
None
2
B
Pour Foundation
A
3
C
Erect Frame
B
4
D
Roof
C
4
E
Windows
C
1
F
Doors
C
1
G
Electrical
C
3
H
Rough-In Frame
D,E,F
2
I
Door Opener
F, G
1
J
Paint
H, I
2
K
Clean Up
J
1
Question 1
0.25
Points
Upload the working calculations that show the critical path, including the forward and backward passes.
Question 2
0.25
Points
What is the critical time for this project?
20 days
18 days
19 days
21 days
Question 3
0.25
Points
There will be a two-day penalty based on the critical time calculated. This statement is:
True
False
Question 4
0.25
Points
What is the total float of the activity "Windows"?
3 days
2 days
1 day
Zero float
Question 5
0.25
Points
What is the free float of the activity "doors", with the successor activity "door opener"?
1 day
zero days
3 days
2 days
Question 6
0.25
Points
After some negotiation with the Simpsons, they have agreed to a new end date. What would the project float be if you had to complete the project in 25 days?
zero days
5 days
7 days
8 days
Question 7
0.25
Points
What is the total float of Activity C - "Erect Frame"?
Zero days
2 days
3 days
5 days
Question 8
0.25
Points
Will you receive a bonus or a penalty at the end based on your original critical time?
Bonus
Penalty
Question 9
0.25
Points
What is the early start (ES) of activity J - "Paint"?
Day 15
Day 17
Day 19
Day 16
Question 10
0.25
Points
A new resource has been assigned to task G "Electrical". This resource takes one day extra to complete the task. The new duration of the task is 4 days. The critical time:
Remains the same
Has increased by 1 day
Has increased by 2 days
The critical time is now 19 days
Question 11
0.5
Points
Use the original information posted for this question.
The task I - "Door Opener" has a specialist working on it. However, a new resource has been assigned and he takes 5 days to complete the task. Based on this change, there are two opinions: the Simpsons and the Project Team. The Simpsons think it will now complete in 22 days, however, the project team thinks it will take 21 days. Who is correct?
The project team
The simpsons
They are both wrong
Details & Information
Assessment due date
3/14/24,8:59 PM (PDT)
You can't submit work after the due date.
You can't make a new submission attempt after due date.
Attempts
1 attempt left
Grading
Maximum points
3 points
Description
This assignment is meant for you to practice the critical path method. Use the PDM network diagramming method to determine the critical time for the project below.You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 21 days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than the agreed 21 days. Draw a project network given the information below. Then, do the following: 1. Complete the forward and backward pass 2. Determine the critical path 3. Compute the Total slack for all activities 4. Determine which activities have free float Then answer the following questions. ...

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!