Question: The Earned Value Management methodology can be used as a means to: A. Forecast future performance based on past performance B. Calculate the number of
The Earned Value Management methodology can be used as a means to:
A. Forecast future performance based on past performance B. Calculate the number of days left in the project C. Calculate the value provided to the customer D. Calculate the profitability of the project