Question: The Earned Value Management methodology can be used as a means to: ( 1 Point ) * Forecast future performance based on past performance. Calculate
The Earned Value Management methodology can be used as a means to: Point
Forecast future performance based on past performance.
Calculate the number of days left in the project.
Calculate the value provided to the customer.
Calculate the profitability of the project.