Question: The estimate at completion (EAC) is the projected or anticipated total final value for a schedule activity, WBS component, or project when the defined work

The estimate at completion (EAC) is the projected or anticipated total final value for a schedule activity, WBS component, or project when the defined work of the project is completed. To determine the EAC, assuming no management intervention, which of the following information is needed? A. The Earned Value (EV) and the Actual Cost to date (AC). B. The Cost Performance Index (CPI) and the Cost Variance (CV). C. The Actual Cost to date (AC) and the Cost Performance Index (CPI). D. The Actual Cost to date (AC) and the Estimate To Complete (ETC).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!