Question: The identification of risks associated with a project happens when? A. Occurs only at the beginning of a project when the risk management plan

The identification of risks associated with a project happens when? ❍ A. Occurs only at the beginning of a project when the risk management plan is developed ❍ B. Is an ongoing process, regularly scheduled throughout the life cycle of a project ❍ C. Occurs as needed throughout the life cycle of a project ❍ D. Both C and D