Question: The main difference between the two types (Arrow Diagramming Method and Precedence Diagramming Method) of the critical path method of scheduling is: A. Depiction of

The main difference between the two types (Arrow Diagramming Method and Precedence Diagramming Method) of the critical path method of scheduling is: A. Depiction of the activity on the logic diagram. B. Arrow Diagramming Method is a deterministic method, whereas the Precedence Diagramming Method is a probabilistic method. C. Precedence Diagramming Method is a deterministic method, whereas the Arrow Diagramming Method is a probabilistic method. D. Arrow Diagramming Method is a more accurate method.