Question: The method of calculating the EAC by assuming the ETC work will be performed at the same cumulative CPI incurred by the project to date

The method of calculating the EAC by assuming the ETC work will be performed at the same cumulative CPI incurred by the project to date is used most often when—

a. Current variances are viewed as atypical ones

b. Original estimating assumptions are no longer reliable because conditions have changed

c. Current variances are viewed as typical of future variances

d. Original estimating assumptions are considered to be fundamentally flawed