Question: The path, or paths, through a project schedule network that represent the most risk because there is no total float is called what? A. Critical
The path, or paths, through a project schedule network that represent the most risk because there is no total float is called what?
A. Critical chain B. Network diagram C. Gantt chart D. Critical path