Question: The responsibility assignment matrix (RAM): A. Is used for development of the project budget. B. Is developed at the activity level and used to closely
The responsibility assignment matrix (RAM): A. Is used for development of the project budget. B. Is developed at the activity level and used to closely link project roles and responsibilities to project network activities. C. Is used to show the connections between work that needs to be done and project team members. It can show responsibilities at various levels of detail. D. Is used to identify accountabilities in individual performance appraisals.