Question: The Responsibility Assignment Matrix (RAM) is: A. Used for development of the project budget and network diagrams. B. Developed at the activity level and used

The Responsibility Assignment Matrix (RAM) is:

A. Used for development of the project budget and network diagrams.

B. Developed at the activity level and used to closely link project roles and responsibilities to project network activities.

C. * Used to illustrate the connections between work packages or activities and project team members. It ensures that there is only one person accountable for any one task to avoid confusion of responsibility.

D. Used to identify accountabilities and responsibilities in individual performance appraisals of project team members.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Managers Questions!