Question: The schedule management plan is a key document. It is a. An output of the develop schedule process b. A tool and technique used in
The schedule management plan is a key document. It is—
a. An output of the develop schedule process
b. A tool and technique used in the develop schedule process
c. The first time management process
d. A separate planning effort completed in conjunction with the time management processes