Question: The three-point estimates method for estimating activity duration differs from the single point, most-likely estimate method in that it uses: A. An average of the
The "three-point estimates" method for estimating activity duration differs from the "single point, most-likely estimate" method in that it uses: A. An average of the three estimated durations to estimate activity duration. B. "Dummy" activities to represent logic ties. C. "Free float" instead of "total float" in the schedule calculations. D. Bar charts instead of logic diagrams to portray the schedule.