Question: If an activity duration cannot be estimated accurately, we should a. Use the average estimate in our critical path method b. Use the worst case
If an activity duration cannot be estimated accurately, we should
a. Use the average estimate in our critical path method
b. Use the worst case estimate in our critical path method
c. Move away from single point estimates and rely on 2 point (best and worst case) estimates
d. Move away from single point estimates and rely on a 3 point (best, worst and most likely case) estimates.