Question: What is the CPI for this project, and what does it tell us about cost performance thus far? a. 0.20; actual costs are exactly as

What is the CPI for this project, and what does it tell us about cost performance thus far?

a. 0.20; actual costs are exactly as planned

b. 0.80; actual costs have exceeded planned costs

c. 0.80; actual costs are less than planned costs

d. 1.25; actual costs have exceeded planned costs