Question: When should you begin risk management on a project? A: When you are completing the monitoring and controlling. B: Once project planning has commenced. C:
When should you begin risk management on a project?
A: When you are completing the monitoring and controlling.
B: Once project planning has commenced.
C: Once project execution has commenced.
D: As soon as a project is initiated or conceived.