Question: When should you begin risk management on a project? A: When you are completing the monitoring and controlling. B: Once project planning has commenced. C:

When should you begin risk management on a project?

A: When you are completing the monitoring and controlling.

B: Once project planning has commenced.

C: Once project execution has commenced.

D: As soon as a project is initiated or conceived.