Question: When the project manager receives a project change request, he should A. Send it to the change control board for approval B. Discuss
When the project manager receives a project change request, he should ❍ A. Send it to the change control board for approval ❍ B. Discuss it with the project team and leave it for phase 2 ❍ C. Evaluate its risk and potential impact before taking any action ❍ D. None of the above